FACTS AND FIGURES
Number and type of turbines | 48 Siemens turbines of 3 MW (SWT 3.0-DD) |
Turbine size | Axle height 95 m, blade-tip height 149 m |
Capacity | The wind farm has a capacity of 144 MW, providing enough sustainable energy for 160,000 households (entire province of Flevoland) |
Reduction of CO2 emissions | 180,000 to 230,000 tonnes per year (fossil compared to fossil power) |
Location | In the IJsselmeer, at 700 to 1,200 metres from the Noordermeer dike and Westermeer dike in the Noordoostpolder. |
Initiators | Farmers Tjitte de Groot and Pieter Meulendijks (Westermeerwind B.V.) |
Partners | Ventolines B.V. supervises the construction work and takes care of operations. Siemens Wind Power provides the wind turbines and builds the Westermeerwind Wind Farm on the basis of a turn key contract. |
Delivery | Spring 2016 |
Planning | 2012-2013: Construction of maritime safety measure (stone dam) 2013: Construction of switching station by TenneT at Westermeer dike 2013-2014: Installation of onshore cabling May 2015: Construction and installation of onshore transformer station completed May 2015: Foundation piles installed July 2015: Installation and protection of farm cabling completed Sept 2015: Start installation of tower sections, turbines and rotors |
Required staff | During the peak period of construction, approx. 300 employees are deployed. During the operational phase, 30 technicians and professionals are deployed, mainly from the region. |